Remodeling work: December 23th - 29th 2017

Submitted by admin on Fri, 12/29/2017 - 15:11

New classroom:

Installing the pillars on the first floor.

Painting the pillars with anti-corrosion paint.

Installing the roof on the classroom space.

Replacing an old wooden pillar.

Expand the corridor.

 

New training/workshop space:

Installing the roof on the training/workshop space.

 

New restroom:

We are making an extra restroom with two ecological toilets.

Preparations for the construction.

Preparing everything to install the ecological toilets.