The remodelling work on the main school building is progressing well. The new roof is now complete. The ramp providing wheelchair access has been laid. Dismantling of the floor and clearing of the floor sub-space is done and the first steel beams to support the floor have been set in place. We expect to have the floor completed by next weekend and the remainder of the work will be complete by the end of the month, God willing. Thank you to everyone who has made this important infrastructure imrpovement possible. |
the base of the ramp for wheelchair access |
|
the steps beside the ramp have been brought forward |
the roof half up |
|
high level transparent fibre glass for better internal light |
the roof 80% up |
|
finishing the last of the roof |
the floor space almost cleared |
|
the main new metal floor support beam |
new metal floor beams for the central teaching area |